Physical Progress

Component % Weightage Physical Progress
(During Current Month)
Physical Progress
(Cumulative, Up to Current Month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB / RUB / Major Bridges / Structures (but excluding Service roads). 56.51% 0.68% 17.11%
Major Bridge works and ROB/RUB 2.74% 0.0% 0.14%
Structures (elevated sections, reinforced earth) 22.94% 0.12% 2.08%
Other works 17.81% 0.01% 0.64%
Total Physical Progress 100% 0.81% 19.96%