action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/ggbhpl/domains/ggbhpl.com/public_html/wp-includes/functions.php on line 6121Project Name | 4-laning of Galgalia-Bahadurganj section of NH327E from Km 00.000 to Km 49.000 (Package-I) on Hybrid Annuity Mode in the State of Bihar. |
---|---|
NH No. (New/old) | NH-327E |
Scheme/Phase | Bharatmala Pariyojna |
Mode of Execution | HAM |
No. of Lanes/Configuration | Four Lane |
Bid Project Cost | 1051 Cr. |
No. Of Bypasses(Name of Town, Length) | 0 Nos. |
No. Of Minor Bridges | New MNB on MCW-09 Nos. Reconstruction of MNB on MCW-07 Nos. |
No. Of Major Bridges | New MJB on MCW-12 Nos. Reconstruction of MJB on MCW-02 Nos. |
No. of Culverts | RCC Box Culverts- New Culverts-43 Nos. Widening /Repairing of Existing Culverts -04nos. |
No. of Elevated Viaducts | 0 Nos. |
No. of FOB | 0 Nos. |
No. of ROB | 0 Nos. |
No. of Underpasses | 09 Nos. |
Toll Plaza | 01 Nos. |
Concessionaire Name | GR Galgalia Bahadurganj Highway Private Limited |
Date of Letter of award(LOA) | 03.03.2021 |
Appointed Date | 10.01.2022 |
Construction Period (in Days) | 730 Days |
Schedule Completion Date | 730 days from Appointed Date |
Operation & Maintenance Period | 15 Years from the Commercial Operation Date |
Independent Engineer | Chaitanya Projects Consultancy Pvt. Ltd. in JV with K & J Projects Pvt. Ltd. |
Authority Name | National Highways Authority of India, PIU-Purnea |
Independent Engineer Mobilization Date | 17.01.2022 |